New Air Traffic Control Tower - Lester B. Pearson International Airport

Client:  Greater Toronto Airports Authority
Prime Consultant:  Chamberlain Architect Services Ltd.
Value:  $1.4 million
Concrete Formwork & Placement: 
Self-Performed


Kenaidan's contract involved the construction of the air traffic control tower's foundation and concrete superstructure.  Work began with the forming and pouring of a 600m³ concrete octagonal foundation mud slab. The next stage was the unique aspects of this project, the slipforming of the 70m high tower.  The slipform superstructure component was completed in 15 days. Forming of two interior stairwells followed the completion of the superstructure.