Greater Toronto Airports Authority Administration

Greater Toronto Airports Authority Administration
Client:  Greater Toronto Airports Authority
Prime Consultant:  NORR LIMITED Architects & Engineers
Value:  $8 million  

The contract for the GTAA's 10,000m2 Administration building and operations Control Centre included extensive refurbishment of the entire building. Architectural, mechanical, electrical, and life safety changes were completed to meet current standards and codes, and the GTAA's operations requirements.  Exterior work included a new concrete entrance canopy, stairs, drop-off roadway, and landscaping.  This project was completed on a fast track, 4 month schedule.

Previous Project   Next Project